Hyundai Transys

Die casting machine — heavy rigging and positioning

A UBE 3,500-tonne die casting machine — 369 tonnes of it — received, moved across a working plant floor and set on its bed, the heaviest section sixty-nine tonnes.

Client
Hyundai Transys
Location
Ramos Arizpe, Coahuila
Period
Aug 2026
Services
Rigging & machine moving
The heaviest package taken off the deck by the 160-tonne crane.

The heaviest package taken off the deck by the 160-tonne crane.

The work

A die casting machine of this size does not arrive as a machine. It arrives in pieces — 369 tonnes of them — and the heavy sections, up to sixty-nine tonnes each, have to cross a working plant floor to reach the bed.

Lifting was done by a 160-tonne mobile crane, but only outside and only where a crane was the right tool. Once a section was through the door it travelled on 32-tonne skates and a 37-tonne forklift, low to the ground — inside a plant that is still running, nothing is carried high. The building gave us a five-metre door and no more, so every package was measured against it before it moved. The bed was welded in place first, then the sections were set onto it one at a time.

The campaign ran three days, inside the six-day window planned for it, with the plant in production the whole time. The machine was accepted by the client on the day it was finished.

One crane, one crew, and a floor that never stopped working.

Scope

  • Reception of six machine packages inside the plant
  • Rigging plan and job safety analysis to NOM-006-STPS-2014
  • 160-tonne mobile crane lifts
  • In-plant transfer on 32-tonne skates and 37-tonne forklift
  • Setting and positioning of all six packages
  • Structural welding of the machine bed
Watch

Videos from the job

A module picked up and brought upright on the 160-tonne crane.
The same module traversed and set down onto its seating.
On site

Photos from the job

Have a line like this to install?

Send us the equipment list and the date you need it running.

info@borbollagroup.com More projects